Preparing 1-phase installations for 3-phase upgrade
Preparing 1-phase installations for 3-phase upgrade
Updated over 3 months ago

It is currently not possible to make a 3-phase bridge to feed Source 2s from a 1-phase fuxe box.

Can I prepare a 1-phase installation for a 3-phase expansion?

No.

What should I do?

You should feed the charger over 1 phase, just L1+N, and nothing else. After the fuse box has been upgraded to 3-phase, someone should come back to the installation to connect L2 and L3. The charger should then be re-configured with the Installer App (which can be done remotely).